A programme you can argue with before work starts
Kolkata · own crews since 2003

A programme you can argue with before work starts

Own crews rather than four layers of subcontract, a week-by-week programme issued with the tender, and a safety plan on site before the first delivery.

What we build

Four kinds of job. Anything outside them is a tender we decline rather than one we learn on.

01

RCC frames

Up to fourteen floors with our own shuttering and steel-fixing crews. The commonest job and the one the whole business is organised around.

02

Industrial sheds

Foundations, plinth and floor to a specified flatness, with the PEB erection coordinated rather than subcontracted blind.

03

Retrofit and strengthening

Jacketing, plate bonding and micro-piling on occupied buildings. Slower, noisier and priced accordingly rather than quoted as though it were new-build.

04

Interior civil

Fit-out civil for offices already handed over. Small tickets we take because the same crews are already in Sector V.

How a job is sequenced

Five steps, and the programme in step two is a document you can mark up rather than a bar chart nobody reads.

1

Site walk, before the price

Access, storage, working hours and what the neighbours will tolerate. Half of what makes a job expensive is decided here and none of it is on the drawing.

2

Programme with the tender

Week by week, naming which trade is on site each week and what has to be finished before it arrives. Issued WITH the price, so you can argue with the sequence rather than only the number.

3

Safety plan before mobilisation

Written, specific to the site and issued before the first delivery rather than pinned up in month two. It names the person responsible, and that person is on site.

4

Weekly measure

Joint measurement every Friday against the programme. A variation is raised in the week it happens, not accumulated into a claim at the end.

5

Handover with the as-builts

Drawings updated to what was actually built, not to what was drawn. The difference matters the first time somebody drills a wall.

Crews and plant

Counted from the muster roll and the plant register — never a safety statistic, which is a claim an audit settles rather than a page.

146
Directly employed, on the muster roll
4
Shuttering systems owned rather than hired
22 yrs
Contracting from Salt Lake

On one job, from the client side

A project manager on a fourteen-floor frame in Rajarhat.

The programme came with the tender and we marked it up before signing. Two of our changes went in and one was refused with a reason — which is the first time in nine years a contractor has argued back at the tender stage rather than at the claim stage.
D
Debjani Sen
Project manager, developer side
14
Floors
19
Months, against 18 programmed
3
Variations raised, all in the week they arose

Send the drawings and the site address

We walk the site before pricing it. If the access or the working hours make the job one we would do badly, that is what the reply says.